How many reviews are included in the permit fees?

The plan review fee covers the initial review of the project final construction documents and all associated minor revisions, shop drawings, and code required submittals. Any revisions with notable work addition or an associated increases in project cost must be reflected in the document review request and or transmittal with additional fees assessed as necessary. Projects that are substantially re-scoped and redesigned must pay for new plan review and inspection fees. Only final construction documents may be submitted for permit review.